Can I keep operating, and until when? A justified and enforceable operating decision.
Fitness-for-service (FFS), risk-based inspection, remaining life, advanced calculations. The repair, replace or operate decision relies on measured data and API codes. The deliverable is not a report: it is a justified, enforceable operating decision.
Equipment covered
Select an equipment item.
Methods
FFS analysis API 579-1 / ASME FFS-1Risk-based inspection (RBI) API 580Quantitative methodology API 581Maximum allowable working pressureMinimum design temperatureMinimum allowable thicknessCorrosion rate and retirement dateFinite element analysisVibration analysisCorrosion and coating assessmentReverse engineering
Applicable standards
API 510API 570API 650API 653API 579API 580API 581ASME